WWTP in Tatenice & Sewage System in Municipalities of Tatenice, Krasíkov, Koruna & Třebařov

Location

Tatenice, Krasíkov, Koruna, Třebařov

Investor

Svazek kanalizace Třebařov

Construction period

10/2014 – 12/2015

Type of construction

Water management

Scope of services

Construction

New waste water treatment plant for 2,250 PE.

The project dealt with draining sewage water from the municipalities of Tatenice, Krasíkov, Koruna and Třebařov into the newly built waste water treatment plant in Tatenice.

The new WWTP is designed as mechanically biological with the capacity of 2,250 PE. The gravity sewage system in the length of 24 km was built, partly using pressure mains (723 m) for overcoming the altitude difference of the terrain. The length of 590 sewer hookups makes 3,442 m in total.

The construction also included building two underground sewage water pumping stations with solid particle separation in the Krasíkov and Třebařov sewage systems.

Job vacancies

Currently, we have several new projects in the pipeline, which open up new career opportunities in our company. Would you like to join our team?

Feel free to contact us!

More in Career

Contact information

VCES a.s. - Head office
Harfa Office Park
Českomoravská 2420/15
190 00 Praha 9

Warning: Fake purchase orders are circulating under the names of Bouygues Construction and the group’s subsidiaries! Fraud attempts using fake purchase orders are on the increase. Protect yourself by carrying out the following checks as a matter of habit:

  • Always pay attention to checking the factual accuracy of the order/document.
  • Check that your contact e-mail address ends with @vces.cz
  • If in doubt, or if you receive a fake e-mail, be sure to get in touch with your usual VCES contact or use the contact form available on this website.

Číst více